Telfer – Mill Ramp

Telfer, Pilbara, Western Australia

CLIENT

Newcrest Mining Ltd.

COMPLETION DATE

Oct-Sept 2019

CATEGORY

Mining

PROJECT DESCRIPTION

In October 2019, Dallcon had awarded with a contract to manufacture and supply precast slabs and footings for a milling project in Pilbara, Western Australia. Given a timeline of only four weeks in design, cast and cure all the 18 units of precast, all were successfully delivered on time.

Precast Ramp Slabs (6000mm Long x 2330mm Wide x 350mm Thick) Anti-Slip finish to tops of panels – Approx. 12.5 Ton each Top & Bottom Slab to have RB16 inserts at 200mm Centres & M20 Ferrules cast in sides 200mm from ends for joining plates with 150m
Precast Footings (6000mm Long x 600mm Wide x 600mm Deep) Approx. 5.2 Ton each M20 Ferrules x 4 each end for joining plates N16 Starter Bars as per drawings.

Other Specs.

  • All Concrete 50Mpa
  • Reinforced Throughout as per Engineer Designs
  • Full MDR Package Included
  • Shop Drawings Included
  • Reid Lifting Engineering Included

CUSTOM PRECAST SOLUTIONS

We supply custom made things ranging from custom panels to other stuff

DOWNLOAD THIS FREE REPORT TO
LEARN WHY CONCRETE MPA MATTERS

TESTIMONIALS

CLIENT SUCCESS STORIES

CONTACT US